Japan nuclear emergency at Fukushima to continue for six to nine months

Sunday, April 17, 2011
By Paul Martin

Malcolm Moore
The Telegraph
April 17, 2011

It was the first time that Tokyo Electric Power company (Tepco) has given a clear timeline for repairing the damage at the plant, and came after repeated complaints at the lack of clear information about the situation.

A phased plan will first target a “cold shutdown” of the plant’s reactor cores, when temperatures are brought down under 100 degrees C.

In the second step, 60,000 tons of radioactive water that currently flood the plant will be “decreased” and decontaminated. Meanwhile the entire building will be covered with a special structure to stop radioactive material escaping.